Sales Order Information
10-12-2023
7701
Closed
SIGNED ESTIMATE
Notes
1 unit Tetrapak Wine Rack Side Attachment PV Board + Acrylic Clips

Aleah to get engineering & PV artwork from BaseCamp Project

PROJECT UPDATES:
10/20/23: Email from Daniel to Aleah that the customer's dimensions have changed. 
10/20/23: Production stopped with Frank. He had bought materials but not started anything.
10/26/23: Customer's new dimensions sent to Vikas to determine if the PV Board + Acryclic needed changed
10/26/23: Daniel/Vikas confirmed that we could proceed with the PV Board but do not make the Acrylic clips
10/30/23: Production re-started with Frank
11/15/23: Sample arrive to iSEE Office and was approved to ship to customer.
NOTE: The bottom base hook was damaged and detached inside the slot when ARCH transfered from the office to Accent. ARCH will credit iSEE for the issue.

PO#3428P - Sent to Frank Monday 10/30/23 with re-started production info. 
Per Frank's info, Aleah estimating total lead time of 15-18 days with delivery to customer by Friday 11/17/23
relayed 22 day lead time to customer after discussion with aleah. = 11/3/23 delivery date

*NOTE: Aleah communicated this lead time to Daniel on the assumption that the product was 100% ready to order at time of PO receipt. As of 10/12/23, we do not have final engineering files or artwork die lines. This may delay the order.
In Chna
PV Board - Need files from BaseCamp
   
NA
UPS Express Saver from Frank to iSEE ($470.82)
ARCH from iSEE Office to Accent 8am-11am Thursday 11/16/23
UPS Next Day Air to Customer (est $60)

Shipping cost factored into total sample cost.
Supporting Notes & Docs
Created on Oct. 12, 2023 at  9:22 AM (CDT). Last updated by Agrawal, Samir on April 23, 2025 at  4:53 AM (CDT). Owned by Bernstein, Daniel.
Daniel Bernstein
Samir Agrawal
Show fields from Show fields from Show fields from a related table
Report Name *
Description
Reports and Charts Panel
Each table has a panel listing its reports and charts, organized in groups.
Please wait while your new report is saved...
Field label
Column heading override
Justification
What does auto mean?
Fields in:

Fields to Extract:

Name for the new table:
Items in the new table are called:

When you bring additional fields into a conversion, Quickbase often finds inconsistencies. For example, say you're converting your Companies column into its own table. One company, Acme Corporation, has offices in New York, Dallas and Portland. So, when you add the City column to the conversion, Quickbase finds three different locations for Acme. A single value in the column you're converting can only match one value in any additional field. Quickbase needs you to clean up the extra cities before it can create your new table. To do so, you have one of two choices:

  • If you want to create three separate Acme records (Acme-New York, Acme-Dallas and Acme-Portland) click the Conform link at the top of the column.
  • If the dissimilar entries are mistakes (say Acme only has one office in New York and the other locations are data-entry errors) go back into your table and correct the inconsistencies—in this case, changing all locations to New York. Then try the conversion again.